|
|
|||||||||||||||||||||||||||||
|
|
|
||||||||||||||||||||||||||||
|
|
|
||||||||||||||||||||||||||||
|
|
|||||||||||||||||||||||||||||
|
|
|||||||||||||||||||||||||||||
|
|
|
||||||||||||||||||||||||||||
|
|
|
||||||||||||||||||||||||||||
|
|
|
|
||||||||||||||||||||||||||
|
|
|
|
|
||||||||||||||||||||||||||
|
|
|
March 2009 Resource (13MB pdf) February 2009 Resource (13MB pdf) January 2009 Resource (13MB pdf) December 2008 Resource (8MB pdf) November 2008 Resource (8MB pdf) October 2008 Resource (9MB pdf) September 2008 Resource (8MB pdf) July August 2008 Resource (8MB pdf)
|
|
|
Electric co-ops halt to
service territory negotiations
A group of municipal utility and electric
cooperative representatives met four times in 2008 and nearly reached
agreement on a formula that would govern electric service territory transfers
involving municipals and cooperatives. The Minnesota Rural Electric Association
(MREA), citing lack of agreement among its members, informed MMUA of its
intention to “suspend” the talks on Dec. 17, 2008. “We are disappointed in the decision to
end the talks,” said MMUA Associate Executive Director Steve Downer. “We felt
the package on the table represented an acceptable give and take between the
two parties.” The MMUA negotiating team identified
numerous separate issues related to service territory. By its tally, the
municipal and cooperative representatives had reached agreement on nearly all
of those issues. The few remaining issues did not appear to be
insurmountable. With momentum seeming to build toward a
settlement, both sides in July appointed representatives to a subcommittee to
work on an appropriate formula for indexing the compensation rate. It never met. On Aug. 20, 2008 the MREA board approved
action to call a recess and cancelled a scheduled Aug. 25 meeting of the full
negotiating teams. On Aug. 29, MMUA told MREA that it was respectful of its
internal political process and ready to resume negotiations whenever MREA was
ready to move forward. The next milestone was the Sept. 12
meeting of the Rural Electric Management Association, where the municipals
had been informed the tentative settlement would be discussed. On Sept. 23,
MMUA received an e-mail that MREA would send a questionnaire to each MREA
member system, and that it expected to clarify its views by mid-December. MMUA wrote to MREA on Dec. 5, reiterating
its appreciation for the work MREA had put into the negotiations, its desire
to resume talks and asking MREA to communicate the results of its December
deliberations in a timely manner. Twelve days later came the letter from
MREA suspending the negotiations. Court
cases led to talks A number of significant regulatory and
legal proceedings set the stage for the talks. Municipals hoped the era of contentious
litigation was ended with an October 2002 Minnesota Public Utilities
Commission ruling on a territory case involving Moorhead Public Service and
Red River Valley Cooperative, where Commission staff scolded the
cooperative’s apparent strategy of adding “delay and cost to the City’s
efforts to provide service, without much compensating protection of the
public interest.” Only a year later, however, things
changed with the ascension of former legislator Leroy Koppendrayer to chair
of the MPUC. In four straight territory cases
(Buffalo, Grand Rapids, Redwood Falls and Otter Tail vs. Lake Region) the
MPUC ignored the findings and recommendations of administrative law judges
and came down squarely on the side of the cooperatives. In two other dockets,
involving Staples and Two Harbors, the MPUC gave interim service rights to
newly annexed areas to cooperatives. This allowed cooperatives to build the
system to serve new customers, complicating municipal efforts and driving up
eventual acquisition costs. The municipals, under this increasingly
troublesome regulatory regime, went to their other option under state law:
proceeding through the eminent domain process in district court. Here, the municipal reasoning—following
standard condemnation theory that payment should be based on the property’s
pre-annexation value—found fertile ground. Both Moorhead and Two Harbors
received decisions from the court-appointed commissioners that followed their
logic. However both municipals, while awaiting appeals to jury trials,
reached compromise agreements with the co-ops to settle the cases. The tentative statewide agreement reached
by MMUA-MREA, perhaps not surprisingly, followed the basics of these
compromise settlements. In both the Moorhead and Two Harbors
cases, the parties agreed to a payment of 15 mills per kilowatt-hour sold
over a period of 10 years. If a new customer were to locate in the area five
years into the agreement, the municipal would pay for the remaining five
years. Much
work, many meetings The MMUA-MREA negotiating teams met in
St. Cloud four times: May 16, June 2, June 19, July 21. The municipals came to the first meeting
willing to listen. In an opening statement, the cooperatives said municipals
and cooperatives were facing larger issues than territory, and needed to work
together on these issues. The cooperatives agreed that the municipal utility
has a right to grow with the city it serves. The municipals made a similar
concession, agreeing to pay for bare ground. Several non-controversial items
were also agreed to. The talks proceeded, sometimes with difficulty but
always with an attempt to understand the other side’s position, from that
point on. The parties gradually built trust as the
generally day-long meetings continued. The talks, almost without fail, were
constructive. The two sides would often ‘caucus’ to consider an offer and
return for further discussion. It appeared that an agreement was within
grasp on July 21. “Little did we know we would not meet
again,” Downer said. In preparation for the meetings, the MMUA
group met, either in person or via conference call, 15 times. MMUA prepared
numerous papers, many of which were shared with the cooperatives. The MMUA group included Arlo Rude of
Thief River Falls, Gary Gleisner of New Ulm, Brad Roos of Marshall, Bill
Schwandt of Moorhead, Steve Shurts of Owatonna, Al Crowser of Alexandria,
Walt Lorber and Larry Koshire of Rochester, Scott Hain of Worthington and Bryan
Adams of Elk River. Additional help was provided by the McGrann Shea law
firm. “MMUA owes a debt of gratitude to the
members who put so much time and effort into these talks,” Downer said. “To
say we were well-prepared for any eventuality is an understatement. That
preparation helped move the talks along, and was largely due to the
tremendous work done by the involved MMUA members. We owe them our thanks.” MMUA remains willing to re-open the
talks. “We were on the brink of an historic agreement
that would have put an end to years of conflict and bickering,” said MMUA
Executive Director Jack Kegel. “The framework that we developed was carefully
constructed to address the key concerns of both sides. We’re very
disappointed that we were unable to complete the process with a settlement so
close at hand. We hope that at some point we will be able to return to the
table and complete the process.” n By Steve Downer Electric co-ops
scuttled other service area settlement attempts
Besides
the 2008 meetings (see preceding article), there have been two other
significant efforts on the part of electric cooperatives and municipal
electric utilities to seek a compromise on the service territory
issue―the COURT process in 1998 and an effort at mediation in 2001. The
first of these efforts resulted from meetings of the Consumer-Owned Utility
Restructuring Team (COURT), a group of representatives from municipals and
cooperatives formed to discuss issues surrounding electric industry
restructuring. The
COURT group held a total of 11 meetings (including one conference call) from
May 1998 through January 1999. The
immediate purpose of the COURT meetings was to discuss possible areas of
agreement concerning electric utility restructuring. However,
the cooperatives wanted to include a discussion concerning service territory
expansion by municipal electric utilities after annexation. There was little
difference in the positions of the two groups on restructuring, but there was
no resolution of the disagreement regarding the service territory issue. No
compromise could be found due to the co-ops’ insistence that any amendment to
the state law concerning municipal territory expansion after annexation
include an eventual territory freeze for municipal utilities. The
municipal utilities refused to surrender the right to grow with their cities,
a historical right which had been reaffirmed by the service territory law
passed in 1974 and which the co-ops had accepted when the law was passed. An
effort to resolve service territory disputes in 2001 between municipals and
cooperatives was initiated by a joint letter from the state legislative
leaders of both parties. In a Sept. 15, 2000 letter to MMUA and the Minnesota
Rural Electric Association (MREA), Senate Majority Leader Roger Moe (DFL,
Erskine), Senate Minority Leader Dick Day (R, Owatonna), Speaker of the House
Steve Sviggum (R, Kenyon) and House Minority Leader Tom Pugh (DFL, South St.
Paul) stated: “As friends of both the municipal
utilities and the cooperatives, we believe the public interest and the state’s electric consumers would be
well served if your organizations would begin discussions this fall in an
earnest attempt to resolve the service territory issue before the start of
the 2001 Legislative Session . . .” Following
several informal conversations, MREA formally accepted a mediation offer made
by MMUA. The
MMUA mediation team made extensive preparations and engaged a mediation
coach. The
parties agreed on the selection of a mediation facilitator but little else.
After three meetings, this effort ended. The municipal team was prepared to
look for common ground to serve as the basis for an agreement, but the
cooperatives were focused on ending the municipal utility right to grow with
the city it serves. n By Steve Downer Co-ops supported municipal right to grow Throughout the history of the electric utility industry,
public policy in Minnesota has provided that a municipal utility may grow
with its city. The electric service territory law, enacted in 1974,
recognized and preserved the long-standing right of cities to provide
electric utility service to all city residents. The law seeks equitable
treatment of all electric ratepayers and taxpayers. It ensures that all city
residents will receive the benefits, or carry the burden, of the utility they
own. The primary proponents of the current service territory law,
which assigns each electric utility a geographic territory, were the rural
electric cooperatives. They were planning to build a major new generating
facility, the Coal Creek Generating Station, in North Dakota. They knew that
they would have to increase rates to pay for the new facility, according to
legislative testimony, and they wanted service territory protection so that
they would have a guaranteed customer base to service their debt. The municipal utilities were willing to agree to the proposed
service territory law, provided that the law preserved the right of municipal
electric utilities to grow with their cities following annexation. The co-ops
accepted this compromise and the bill was enacted, providing service
territory protection for the co-ops while preserving the municipal utilities’
right to grow with the city. Harold LeVander, Jr., speaking for the cooperatives before the
House Committee on Governmental Operations on April 19, 1973, said, “We’re
providing in this bill, because of the public nature of the municipally owned
system, that they can buy out based on a formula that’s provided in here, the
facilities of any power supplier in their area—if they expand. In other
words, we’re preserving, really, the right of municipally-owned systems to
continue to expand with their corporate borders should annexations occur.” State law lists four factors to consider when determining the
price a municipal should pay to acquire the territory of another utility. The
law does not contain a specific formula, however. Over time and a due to a number of regulatory rulings,
municipal utilities routinely pay, for sales in bare ground areas, as if the
area had been fully developed. Even the Minnesota Public Utilities Commission (MPUC) has
acknowledged, in the Rochester ‘North Park’ case, that “the co-ops are now
receiving significantly greater compensation than that which was envisioned
at the time the law was passed.” Some semblance of balance has swung back toward the municipals
with recent district court eminent domain cases. That chain of events led to the 2008 talks between municipals
and co-ops. A solution, however, remains elusive. n By Steve Downer |
|
|
TATTLER
|
|
|
|||||||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
|
||||||||||||||||||||||||
|
|
||
|
|
Minnesota Municipal Utilities Association
|
|
|
|
|
|